Ash, Canterbury - Renewable Development

Ash, Canterbury

Renewable Development

At a Glance

Dragon Infrastructure Solutions successfully completed a large CHP project for APS Salads, totalling 15MW export, tucked away in Ash on the outskirts of Canterbury. The challenge was to connect 2NO – 7.5MW 11kV combined heat and power plants to the UKPN DNO grid via a new 33kV metering substation.

The farm covered 52 acres of land and was designed to provide enough electricity to power more than 4,300 homes making it an important development for the local area. Dragon IS, one of the UK’s leading independent connections providers, designed and installed the entire connection framework from the 33kV metering substation along with 2.9 km of 33kV cable to the 33/11kV 15 MVA transformer. The cables and metering substation were then adopted by UKPN.

Want an electricity distribution network designed and installed to meet your needs, your budget and your deadline? We should talk.

Download Case Study PDF

Our Solution

  • 33kV connection to overhead power lines
  • Designed and installed 2.9 km of 33kV cable
  • The design and installed cable was adopted by UKPN
  • Designed and installed 33kV metering substation for adoption by UKPN
  • Designed and installed Customer 33kV and 11kV switchroom
  • Designed and installed Customer 33/11kV 15 MVA Transformer
  • Designed and installed 11kV distribution for site – including 500 meters of 11kV cable and distribution substation